Solar-A
Implementation
Process | Status |
---|---|
1. Surveying |
Completed
|
2. Land acquisition |
Completed
|
3. Soil testing | |
4. Levelling |
Completed
|
5. Designing of layout |
Completed
|
6. Marking on field |
Completed
|
7. Construction of roads |
In-Progress
|
8. Construction of MCR |
In-Progress
|
9. Installation of module structure |
In-Progress
|
10.Installation of modules |
In-Progress
|
11. Cable laying |
In-Progress
|
12. Installation of invertors |
In-Progress
|
13. Installation of switchyard |
In-Progress
|
14. Installation of HT panels |
In-Progress
|
15. Commissioning of plant |
In-Progress
|
Operational